The use of Building Information Modelling (BIM) 5D technology in the
construction industry has become an innovative solution for project cost planning and
control. This study aims to evaluate the effectiveness and accuracy of BIM 5D
implementation in preparing Engineering Estimates using Glodon Cubicost software
(TAS, TRB, and TBQ). The case study was conducted on the Construction Project of
the Coordinating Ministry Office Building and Area 1 – Nusantara Capital City (IKN).
The research method was carried out by comparing the results of work volume
calculations and cost estimates using BIM 5D with conventional methods based on
Microsoft Excel. The results indicate that the implementation of BIM 5D produces
more accurate calculations of structural and architectural work volumes compared to
conventional methods, with differences of 4.6% in concrete work, 15.67% in
formwork, 14.95% in reinforcement work, 3.95% in brick wall installation, and
47.41% in plastering and wall finishing work. In addition, BIM 5D accelerates the
preparation process of Engineering Estimates, facilitates cost adjustments due to
design changes, and improves cost estimation transparency. The integration of BIM
5D also supports project progress monitoring and assists decision-making during
project implementation, particularly in addressing design errors or changes occurring
in the field
| Tipe Dokumen: | Skripsi |
|---|---|
| Tipe: | Skripsi |
| Jurusan: | Program Studi Teknik Sipil |
| Depositing User: | Dept Perpustakaan Jakarta Global University |
| Date Deposited: | 15 Oct 2026 04:36 |
| Last Modified: | 15 Oct 2026 04:36 |
| URI: | https://digilib.jgu.ac.id/id/eprint/713 |